Effort reports from Rob Gardner

Background

The OSG WBS is located here. My activity (0.5 FTE) maps mostly into WBS 1.1.3 (OSG Y1/Facility/Integration).

Current effort reports

See here for up to date effort reports (effective 11/26/07).

Previous effort reports: 2007

Period: December 2006

Period: November 2006

Description:

I am working on:
  • SOW for UC DONE
  • Planning activity for IntegrationProject
  • Coordination of the Integration activity - weekly meetings, see Integration.Meetings: DONE
  • Validation testbed
    • Setting up software cache for the VTB at UC (gave to Suchandra) DONE
    • Locate/specify server hardware at UC DONE
    • Setup of an RT queue for issue tracking DONE
  • Deploying a site on a UC development cluster for ITB 0.5.1. DONE
  • Deputy Executive Director duties
    • Weekly ET meetings reporting on integration issues DONE
    • Start working on metrics

Issues

  • Need to get OSG project plan editing for Integration related activities. DONE
  • Need to solidify project effort for Integration: DONE
    • From UC: 0.5 Suchandra Thalpa
    • From CIT: David Meyers
    • From LBL: Jeff Porter (and Shreyas Choila as backup)

-- RobGardner - 29 Nov 2006

Topic revision: r38 - 03 Dec 2007 - 11:28:08 - RobGardner
Hello, TWikiGuest
Register

OSG Reports
  • add items

Meta-TWiki links

 
TWIKI.NET

TWiki | Report Bugs | Privacy Policy

This site is powered by the TWiki collaboration platformCopyright by the contributing authors. All material on this collaboration platform is the property of the contributing authors..