RPM Transition Plan

Jump to the current state (Skip the background information)

Goal

Our goal is to provide the following functional units as RPMs for Red Hat Enterprise Linux 5, Scientific Linux 5, and CentOS 5 by December 13, 2011:

  • glexec
  • Worker Node Client
  • Client (i.e. worker node client + end-user tools)
  • Compute Element (CE)
  • RSV (Earlier discussions included this in the CE, but we've separated it.)
  • BeStMan, Hadoop & BeStMan, Xrootd & BeStMan (SE)

This does not account for everything in the existing Pacman-based VDT. Additional functional units will come in early 2012, the time to be determined:

  • GUMS
  • Gratia Collector

In addition to the above functional units, we have two more major areas of focus that cut across all of the functional units and need attention beyond that in the developing the functional units.

  • Internal testing infrastructure
  • Documentation

Release Process

For each functional unit in the VDT, we will proceed through a series of steps, shown here. Steps 4a, 4b, and 4c can be performed in parallel.

rpm-package-process.png

The tables below show when we complete each step--they are milestones, not periods of time for each state.

Definition of steps

1. Package
This is the time where we will construct the set of RPMs for the given functional unit. Note: We expect some very basic documentation at this point.

2. Internal Testing
This is the time where we do basic, hands-on developer testing of the RPMs.

3. Fix known problems
We are allocating time to fix problems. While it is hard to know what problems we will encounter, we recognize that we will make an educated guess so that when we run into the inevitable problems, fixing them fits into our schedule.

4a. Documentation
This is the time when we move the existing basic documentation to something that fits into our documentation structure and is usable by end-users.

4b. Evaluation
We might do an extensive internal evaluation for scalability or readiness. For instance, evaluating the scalability of GRAM 5. Not all functional components will need this.

4c. External Beta Testing
We will work with one or two selected external sites to do testing. This is outside the ITB testing: we will work closely with them to get early feedback.

4d. Integration Testbed
Testing by the integration testbed.

5. Limited Release
We release the software into production. We do not widely announce it, and our ability to provide support is limited (but available). This is a release meant for early adopters.

6. General Release
We release the software into production. We announce and fully support the previously created limited release.

States

Steps can be in five different states:

Not StartedNeither started, nor expected to be started
 On Track 
Progress is being made, no worries about meeting deadline
 Behind 
Behind schedule, but may be able to catch up. Not yet at risk.
 At risk 
At risk, deadline may not be met
 Achieved 
Goal has been achieved

Summary as of 13-Dec-2011

In the table below, State can be one of:

  • Developing: Not ready for testing, still being prepared
  • Stable: Ready for testing, only essential changes will be made before release.
  • Mixed: Portions are developing, portions are stable.
  • Released: Has been released, limited or production.

Functional Unit State Target Limited Release Target General Telease Summary
VOMS
 Released 
4-Oct-2011 1-Nov-2011
VOMS has had it's general production release.
It is deployed in production for Engage, HCC and GLOW
glexec
 Released 
1-Nov-2011 29-Nov-2011 Glexec has had it's limited production release.
Worker Node
 Released 
1-Nov-2011 29-Nov-2011 The worker node has had it's limited production release.
Client
 Released 
1-Nov-2011 29-Nov-2011 The client has had it's limited production release.
CE
 Released 
29-Nov-2011 13-Dec-2011 In testing in ITB and at Fermilab Tier 1 ITB
RSV
 Released 
29-Nov-2011 13-Dec-2011 RSV is ready for testing and has been given to ITB.
SE
 Released 
    Bestman, Xrootd, and HDFS are stable and ready for testing.
Documentation N/A, see below N/A, see below Docfest was Oct 10-12. Documentation
Internal Testing Framework N/A N/A N/A Have basic testing framework in place, Mat will write tests soon.
Security
 Released 
4-Oct-2011 1-Nov-2011 In production, limited release

Weekly Highlights

Date Note
13-Dec-2011
OSG Software 3.0.5 was released.
CE, SE, and RSV are now all in general production release
6-Dec-2011
Today we shipped OSG Software 3.0.4.
It updates the general release of VOMS, the clients, and glexec
It also includes the limited release of the CE, RSV, and the SE (Bestman & HDFS)
CMS, ATLAS, Dzero, and DOSAR have all signed off on the release
More evaluation will continue at UCSD to test GRAM further, but GRAM is working quite well.
29-Nov-2011
Today was the general release of the client, worker node client, and glexec
Most GRAM bugs have been resolved, with one major bug pending. We have delayed our limited release of the CE and RSV until next week to do a thorough job of testing GRAM and fix remaining bugs.
Dzero has verified that their jobs work with the new RPM-based VDT.
22-Nov-2011
Today was the limited release of Xrootd
9-Nov-2011
Finished internal testing of Globus update, will go to ITB and testing sites later today
Nebraska is running two production CEs with the new RPM-based install.
Testing with PBS is in progress and going well
2-Nov-2011
Yesterday was the general release of VOMS
Yesterday was the limited release of worker node client, client, and glexec
In the last week, we found and fixed a serious scalability problem with the CE, doing more testing.
25-Oct-2011
We've updated to Xrootd 3.1 and hope to release "soon"--depends on external beta testing.
We've completed the HDFS transition to the VDT repo.We found and fixed a serious problem with lcmaps (used for authorization with GUMS from the CE).
Engagement has deployed the new RPM-based VOMS server successfully
19-Oct-2011
Doc Fest was last week. Lots of documentation is done and in good shape, but we have quite a bit remaining.
The CE became stable last week when the GIP and CEMon became feature-complete. Testing is ramping up quickly. In particular, the Fermilab Tier-1 ITB has a CE and its worker nodes using RPMs, and it will be tested with glideinWMS soon.
Several ITB sites are actively testing and providing good feedback.
6-Oct-2011
We released VOMS and the CA certificate packaging on October 5!
The evaluation group is doing scalability testing with GRAM.
To finalize the CE, we need a small GIP update and some fixes to osg-configure.
28-Sep-2011
We got an update for Globus to deal with our compatibility problem.
CEMon is nearly ready, final readying should be done in a day or two.
All software is now in osg-testing repository.
Suchandra is gone, but Alain will bootstrap ITB testing
20-Sep-2011
After a couple of bumps, we are now proceeding full speed on testing. A few specifics:
Globus 5.2.latest is now in the VDT.
Our evaluation team at UCSD has given its blessing to GridFTP?--it is performing well and we are comfortable with it.
Condor-G linked against Globus 5.2 fails and revealed a compatibility problem. Globus is addressing it.
Our RPMs are now cryptographically signed
The CE is ready for testing, except for CEMon, but CEMon is on its way
RSV is ready for testing
We have our first testing done in our testing framework
31-Aug-2011
All prepped and awaiting Sep 2 release of GT 5.2 beta
Now have doc, SE, security, and testing plans from owners.
24-Aug-2011 Globus 5.2 complications:
Globus 5.2 update is underway. As of last week thought we could do a drop-in replacement without rebuilding any packages that depend on Globus, but as of yesterday we learned this is not true. This complicates the push into EPEL. For now we are pushing all of Globus 5.2 and packages we use from EPEL that depends on Globus 5.2 into the VDT. This lets us meet our goals, but reduces full compatibility with the EPEL repository.
23-Aug-2011 I'm worried about documentation because I do not yet have a plan or progress from Robert or Jim.
22-Aug-2011 glexec is ready for friendly testing.
19-Aug-2011 Updated plan with limited and general release dates. Worker node is being tested in ITB
3-Aug-2011 We have completed internal testing on the OSG client and the VOMS server!
We are nearly ready for the OSG site admin meeting, except for some minor glexec issues and basic docs for glexec and the OSG client

Functional Unit: VOMS

VOMS has been released! It is in general release, which means we have widely announced it. It's been deployed in production at three sites (Engage, HCC & GLOW).

Milestone State Owner Target Start Target Finish Actual Finish Notes
1. Package
 Achieved 
Brian 18-July-2011 25-July-2011 28-July-2011 #26
2. Internal Testing
 Achieved 
Tanya 25-July-211 1-Aug-2011 2-Aug-2011 #99
3. Fix known problems
 Achieved 
Tanya 1-Aug-2011 8-Aug-2011 2-Aug-2011
No problems found during internal testing
(but lots found & fixed during packaging)
4a. Documentation
 Achieved 
Marco, Tanya 29-Aug-2011 9-Sep-2011 11-Oct-2011 VOMS install documentation is usable but is still being reviewed.
4b. Evaluation N/A N/A N/A N/A   Relying on external beta testing
4c. External Beta Testing
 Achieved 
Suchandra 15-Aug-2011 30-Sep-2011 4-Oct-2011 Deployed in production by HCC and GLOW
4d. Integration Testing N/A Suchandra N/A N/A   Relying on external beta testing
Milestone State Target Release Actual Release Notes
5. Limited Release
 Released 
4-Oct-2011 5-Oct-2011 Has been deployed by Engage, HCC, and GLOW
6. General Release
 Released 
1-Nov-2011 1-Nov-2011  

Functional Unit: glexec

glexec has been released.

Milestone State Owner Target Start Target Finish Actual Finish Notes
1. Package
 Achieved 
Brian 7-July-2011 25-Jul-2011 15-Jul-2011 #17
2. Internal Testing
 Achieved 
Brian 25-July-2011 1-Aug-2011 15-Jul-2011  
3. Fix known problems
 Achieved 
Dave Dykstra 1-Aug-2011 8-Aug-2011 22-Aug-2011 Late because effort relied on limited non-OSG Software Team effort.
4a. Documentation
 Achieved 
Dave Dykstra 1-Sept-2011 23-Sept-2011 11-Oct-2011 Glexec install documentation
4b. Evaluation N/A N/A N/A N/A   Not needed right now. (May add scalability testing later on.)
4c. External Beta Testing
 Achieved 
Suchandra 15-Aug-2011 28-Oct-2011 31-Oct-2011  
4d. Integration Testing
 Achieved 
Suchandra 1-Sep-2011 28-Oct-2011 28-Oct-2011  
Milestone State Target Release Actual Release Notes
5. Limited Release
 Released 
1-Nov-2011 1-Nov-2011  
6. General Release
 Released 
29-Nov-2011 29-Nov-2011  

Functional Unit: Worker node client

The worker node client is ready for friendly testing and documentation. It is in testing in the ITB as well as at Nebraska and Fermilab Tier 1 ITB. We recently fixed a problem with missing software (LFC Python bindings) found in the ITB. It has been tested with glideinWMS by the evaluation team.

Milestone State Owner Target Start Target Finish Actual Finish Notes
1. Package
 Achieved 
Derek 6-July-2011 25-July-2011 15-July-2011 #1
2. Internal Testing
 Achieved 
Derek 25-July-2011 1-Aug-2011 15-July-2011  
3. Fix known problems
 Achieved 
Derek 1-Aug-2011 8-Aug-2011 15-July-2011  
4a. Documentation
 Achieved 
Suchandra 29-Aug-2011 9-Sep-2011 11-Oct-2011 Worker node install documentation (2 Total)
4b. Evaluation N/A Igor N/A N/A  
Evaluation team is focused on CE, but has done basic testing of worker node with glideinWMS.
4c. External Beta Testing
 Achieved 
Suchandra 15-Aug-2011 24-Oct-2011 28-Oct-2011 Tested by Nebraska & Fermilab Tier 1 ITB
4d. Integration testing
 Achieved 
Suchandra 22-Aug-2011 28-Oct-2011 28-Oct-2011
Tested by BNL, FNAL, FNAL (CMS), OUHEP, TTU, and UC_ITB ITB sites
Will continue testing with workloads during CE testing
Milestone State Target Release Actual Release Notes
5. Limited Release
 Released 
1-Nov-2011 1-Nov-2011  
6. General Release
 Released 
29-Nov-2011 29-Nov-2011  

Functional Unit: Client

The client has been released.

Milestone State Owner Target Start Target Finish Actual Finish Notes
1. Package
 Achieved 
Derek 6-July 25-July-2011 15-July-2011 #4
2. Internal Testing
 Achieved 
Marco 25-July-2011 1-Aug-2011 3-Aug-2011 Test ticket: #98
3. Fix known problems
 Achieved 
Derek 1-Aug-2011 8-Aug-2011 3-Aug-2011  
4a. Documentation
 Achieved 
Marco, Robert, Suchandra 1-Aug-2011 23-Aug-2011 10-Oct-2011 Install client documentation
4b. Evaluation
 Achieved 
Igor 23-Aug-2011 9-Sep-2011 31-Oct-2011 Limited testing, due to focus on CE
4c. External Beta Testing
 Achieved 
Suchandra 12-Sep-2011 28-Oct-2011   Was tested by Evaluation team, and Fermilab ITB Tier 1
4d. Integration Testing
 Achieved 
Suchandra 12-Sep-2011 28-Oct-2011    
Milestone State Target Release Actual Release Notes
5. Limited Release
 Released 
1-Nov-2011 1-Nov-2011  
6. General Release
 Released 
29-Nov-2011 29-Nov-2011  

Functional Unit: CE

The CE has been released.

Milestone State Owner Target Start Target Finish Actual Finish Notes
1. Package
 Achieved 
Mat (Brian) 20-July-2011 29-Aug-2011 16-Sep-2011 Late due to Globus 5.2 update.
2. Internal Testing
 Achieved 
Mat (Brian) 29-Aug-2011 12-Sep-2011 26-Sep-2011 Late due to Globus 5.2 update.
3. Fix Known Problems
 Achieved 
Mat (Brian) 12-Sep-2011 27-Sep-2011 26-Sep-2011  
4a. Documentation
 Behind 
Marco, Suchandra, Steven, Tanya 27-Sep-2011 21-Oct-2011  
Have early documentation.
Nearly completed
See Doc List (25 Total)
4b. Evaluation
 Achieved 
Igor 19-Sep-2011 21-Nov-2011 5-Dec-2011
Currently testing recent bug fixes, which is taking longer than expected
Eval group has tested 1000 jobs with success
Working with long-running test (24 hours)
4c. External Beta Testing
 Achieved 
Suchandra 19-Sep-2011 21-Nov-2011 5-Dec-2011
GRAM bugs have been found, hence extending the testing period
CMS Tier 1 ITB CE has been installed (CE + WN) & tested with glideinWMS
Nebraska has 4 CEs installed, has found and debugged many problems.
4d. Integration Testing
 Achieved 
Suchandra 19-Sep-2011 28-Nov-2011 5-Dec-2011
GRAM bugs have been found, hence extending testing
Dzero has signed off on release
glideinWMS jobs are working
ATLAS HammerCloud? will be run very soon
ITB Sites testing: https://twiki.grid.iu.edu/bin/view/Integration/ITBRPMTestSite
VO test results: https://twiki.grid.iu.edu/bin/view/Integration/RPMVoTesting
Milestone State Target Release Actual Release Notes
5. Limited Release
 Released 
29-Nov-2011 6-Dec-2011  
6. General Release
 Released 
13-Dec-2011 13-Dec-2011  

Functional Unit: RSV

RSV has been released.

Milestone State Owner Target Start Target Finish Actual Finish Notes
0. Develop
 Achieved 
Scot 20-July-2011 9-Sep-2011 12-Sep-2012
Work led by Scot, who is at 25% OSG time
Major remaining work includes:
Condor configuration for separate condor-cron
Update probes to run in RPM environment
Use Condor-G instead of globus-job-run</>
1. Package
 Achieved 
Scot 20-July-2011 9-Sep-2011 12-Sep-2012  
2. Internal Testing
 Achieved 
Scot 6-Sep-2011 12-Sep-2011 12-Sep-2012 Internal testing done while developing & packaging. Found Condor-G problem, not an RSV issue
3. Fix Known Problems
 Achieved 
Scot 12-Sep-2011 19-Sep-2011 4-Oct-2011 It took longer than expected to fix cacerts-expiry probe, but it's now ready.
4a. Documentation
 Behind 
Scot 19-Sep-2011 26-Sep-2011   Documentation is usable but incomplete.
4b. Evaluation N/A N/A       Not needed for RSV.
4c. External Beta Testing
 Achieved 
Suchandra 19-Sep-2011 28-Nov-2011 5-Dec-2011  
4d. Integration Testing
 Achieved 
Suchandra 19-Sep-2011 28-Nov-2011 5-Dec-2011 Has been given to ITB. Initially was delayed due to CE being delayed.
Milestone State Target Release Actual Release Notes
5. Limited Release
 Released 
29-Nov-2011 6-Dec-2011  
6. General Release
 Released 
13-Dec-2011 13-Dec-2011  

Functional Unit: SE

The Storage Element (Bestman2, HDFS, & Xrootd) has been released.

Milestone State Owner Target Start Target Finish Actual Finish Notes
1. Package
 On Track 
Tanya pre-history 16-Sep-2011  
Xrootd was packaged in May.
!BeStMan was packaged inJuly.
HDFS is being started in late August: #186
Fix xrootd-dsi setup.sh script #215 is being started in late August
Create metapackages:
gridftp/lcas: #204 started in late August, due date 9/31/11
osg-se-bestman: #206 depends on #204
osg-se-xrootd: #210 depends on #204, #215
2. Internal Testing
 On Track 
Tanya pre-history 23-Sep-2011  
test dCache-storage: #66 started in late August, due date 9/31/11
test dCache-transfer: #67started in late August, due date 9/31/11
test gridftp/lcas/lcmaps metapackage: #205 depends on #204
test osg-se-bestman-xrootd metapackage : #211 depends on #210
test xrootd-storage: #73 depends on #210
test xrootd-transfer: #73 depends on #210
test GridFTP? gratia probe: #64depends on #204
3. Fix Known Problems
 On Track 
Tanya 23-Sep-2011 30-Sep-2011    
4a. Documentation
 On Track 
Tanya, Doug, Jeff pre-history TBD  
XRootd docs were done in May
!BeStMan yet to be done.
Can build on existing HDFS docs,
Need to document gridftp and lcas/lcmaps configuration as well as all gratia storage and transfer probe by end of September
write documentation for grdiftp-lcas metapackage installation/configuration #209
See Doc List (14 Total)
4b. Evaluation
 On Track 
Igor pre-history 29-Nov-2011 29-Nov-2011
Xrootd and Bestman were evaluated by ATLAS
HDFS was evaluated by CMS
4c. External Beta Testing %ACHIVED% Suchandra 3-Oct-2011 29-Nov-2011 5-Dec-2011 Tested by Jeff Dost, people in ATLAS (Bestman/Xrootd), and in CMS (Xrootd)
4d. Integration Testing Not Started Suchandra 3-Oct-2011 29-Nov-2011 5-Dec-2011  
Milestone State Target Release Actual Release Notes
5. Limited Release
 Released 
6-Dec-2011 6-Dec-2011  
6. General Release
 Released 
13-Dec-2011 13-Dec-2011  

Documentation

This doesn't match the process diagram above because it is not about packaging but documenting the packages.

Docfest was October 10-12. All the documentation is good enough for our December releases, but we agree that it's still a bit rough. We are likely to have another documentation fest (one or two days long) in January 2012.

Milestone State Owner Target Start Target Finish Actual Finish Notes
Create Twiki Web
 Achieved 
Robert/Kyle 1-Aug-2011 8-Aug-2011 30-Aug-2011 Have web and plan for future releases
Prototype: Worker Node Install
 Achieved 
Suchandra 8-Aug-2011 30-Aug-2011 30-Aug-2011 Suchandra created document
Prototype: VOMS Install
 Achieved 
Marco 15-Aug-2011 30-Aug-2011 30-Aug-2011 Marco created document, ready for review.
Report: How hard is RPM documentation
 Achieved 
Robert 22-Aug-2011 30-Aug-2011 30-Aug-2011 Have identified all documents and estimate typical install document will take about 3 hours - total of 90 documents with references to VDT_LOCATION
Create common documents for RPM
 Achieved 
Jim, Brian, Alain, Suchandra 29-Aug-2011 16-Sep-2011 15-Sep-2011 See 4 documents. Brian has draft of Install Best Practices and we have outline of YumRpmBasics.
Create Landing Page Instructions
 Achieved 
Robert 6-Sep-2011 13-Sep-2011 13-Sep-2011 Landing pages created in Release3 web with comments on needed content and existing links that need to be referenced.
Documentation Fest
 Achieved 
Jim Early Oct 15-OCT-2011 12-Oct-2011 Bring together about 10 people to work for 3 days updating documentation that is needed/behind and produce set of Navigation landing pages.

Automated Integration Tests

State

We have a set of tests running daily and reporting results. We are working on expanding the tests.

Backround

This doesn’t match the process diagram above because it is not about packaging but testing our packages.

While we have done a lot of testing with Pacman, our system cannot simply be ported to work with RPMs--it is deeply intertwined with Pacman. Some of our existing problems

  • The installation mechanism is entirely different
  • Most of the tests to verify a Pacman installation was sane no longer apply to an RPM installation
  • The testing framework we used does is shaky and ancient
  • The new tests will need to be run in an entirely different way (clean VMs or fresh machine installs)

We trying to balance the need to get some testing as soon as possible with the need to have a coherent system on which to build. The first few steps of this plan get some basic (manual) testing in place without building a comprehensive framework. Because we have significant uncertainty and because we will learn a lot during this time, we explicitly include a planning step at the end of September. At no point will we engineer a massive new system, but we will phase in the testing architecture appropriately.

If the external dependency on the Batlab slips significantly, we will do testing temporarily in FermiCloud.

Milestone State Owner Start Target Finish Actual Finish Notes
Finish plan for Phase 1
 Achieved 
Tim 1-Aug-2011 31-Aug-2011 31-Aug-2011 Had productive discussion with Batlab and team members
Batlab provides ability to run VMs
 On Track 
Batlab 4-Aug-2011 3-Oct-2011   External dependency (Batlab), dates may change, tracking closely
Manually run 1 test of 1 package on 1 platform
 Achieved 
Tim 29-Aug-2011 9-Sep-2011 12-Sep-2011 Testing grid-proxy-init hits most technical issues
Add a cross-section of tests (10-20) to manual run
 Behind 
Marco 9-Sep-2011 23-Sep-2011  
Work delayed due to previous slip, and due to preliminary work for LIGO packaging
Tim has added tests for GridFTP?.
Transitioning to Marco, but Marco was delayed due to work on RSV probe.
Replan based on new experience
 Behind 
Tim 26-Sep-2011 30-Sep-2011   Not started, waiting for previous step to complete. Plan will include the items below, based on what we learn
Manually submit tests of 1 package on 1 Batlab platform
 Achieved 
TBD 1 week   Depends on Batlab schedule
Auto-submit tests of 3–5 packages on 3 Batlab platforms
 Achieved 
TBD 1 week   Follows 1-on-1 Batlab task
Archive test results and show via simple mechanism Not Started TBD 2 weeks?   What web application system?
Expand system to control order that tests run Not Started TBD        

Security

In collaboration with the OSG Security Team, we are doing three things:

  1. Making source RPMs for the CA certificate distributions.
  2. Porting and updating vdt-update-certs and vdt-ca-manage
  3. Ensuring that the Security Team can maintain the osg-cert-scripts. (Previously known as the ppdg-cert-scripts and originally maintained by Doug Olson.)

These are not blocking other work because we have a hacked version of the the CA certs that is sufficient for testing purposes. However, it does block releases, so we are trying to get this through testing relatively quickly. Because the packaging was finished ahead of schedule, we have shifted the date from their originals to release earlier. See below.

The security team owns the planning for this section.

Milestone State Owner Target Start Target Finish Actual Finish Notes
1. Package
 Achieved 
Scot 22-Aug-2011 9-Sep-2011 30-Aug-2011
#152
#153
#154
#155
#156
Spec files for all the three packages are in place
2. Internal Testing
 Achieved 
Anand 2-Sep-2011
(orig. 9-Sep-2011)
9-Sep-2011
(orig. 16-Sep-2011)
12-Sep-2012  
3. Fix Known Problems
 Achieved 
Anand 9-Sep-2011
(orig. 16-Sep-2011)
16-Sep-2011
(orig. 23-Sep-2011)
12-Sep-2012  
4a. Documentation
 Achieved 
James, Anand, Doug 16-Sep-2011 30-Sep-2011 29-Sep-2011 The essential documentation is done.
4b. Evaluation N/A N/A       Evaluation by Igor's team not needed
4c. External Beta Testing N/A N/A       External beta testing not needed--heavily used by other components
4d. Integration Testing
 Achieved 
Suchandra 16-Sep-2011 30-Sep-2011 4-Oct-2011 Was a bit late in getting to ITB
Milestone State Target Release Actual Release Notes
5. Limited Release
 Released 
4-Oct-2011 5-Oct-2011
The release dates were originally in December, but we need this for the VOMS release.
6. General Release
 Released 
1-Nov-2011 1-Nov-2011  

Functional Unit: GUMS

DEFERRED TO 2012

We will package GUMS before the end of the year if possible. This is a low priority goal: we will focus on the CE and exclude GUMS if necessary. For the short-term this is acceptable because GUMS can still be installed via Pacman.

Functional Unit: Gratia Collector

DEFERRED TO 2012

This is a low priority goal: we are not aiming to have progress on it during 2011 unless we have spare time.

Functional Unit: CREAM

DEFERRED TO 2012

CREAM will not be part of our RPM release in 2011.

Topic revision: r89 - 10 Jan 2012 - 21:28:01 - AlainRoy?
Hello, TWikiGuest
Register

 
TWIKI.NET

TWiki | Report Bugs | Privacy Policy

This site is powered by the TWiki collaboration platformCopyright by the contributing authors. All material on this collaboration platform is the property of the contributing authors..